z Systems Solution Sales V7 C9030-633 exam is an ultimate source to boost your career. The IBM C9030-633 exam dumps material is strictly designed by the subject matter experts, after an in-depth analysis of IBM recommended material. The IBM C9030-633 exam increases your ability in various domains, such as Gather Customer Requirements, Develop Business Solution and Business Resiliency. We at OnlineExamDumps provide you latest C9030-633 exam questions. A candidate will be allocated 90 minutes to complete the exam and its important for them to must score 70% marks in the score.

Version: 7.0

Question: 1

A customer runs eight-day-long disaster recovery tests at a remote data center using disk and a CEC with minimal processing capacity.
Which of the following is the most cost-effective method to provide enough processing capacity for testing purposes?

A. Capacity for Planned Events (CPE)
B. On/Off Capacity on Demand (OOCoD)
C. Customer Initiated Upgrade (CIU)
D. Capacity Backup (CBU)

Answer: A

Explanation:
Reference:
http://www-304.ibm.com/services/weblectures/dlv/partnerworld/online/ltu28080/capacity%20on%20demand.ppt (Slide 3)

Question: 2

New Updated C9030-633 Exam Questions C9030-633 PDF dumps C9030-633 practice exam dumps: https://www.dumpsschool.com/C9030-633-exam-dumps.html (74 Questions)

A customer has identified their workload requirements for a replacement z Systems processor. The sizing has been completed. The CIO is considering a three-year plan for this upgrade. The CIO is asking the sales specialist for advice.
Which of the following capabilities allow customers to better manage their workload requirements, considering cost and growth?

A. IBM SmartCloud and CloudBurst
B. Specialty Engines and Linux
C. Granularity and Capacity on Demand
D. Plan Ahead Capacity and CBU

Answer: C

Question: 3

A prospective new z Systems customer is interested in an entry-level system with the lowest cost application development environment. There should be options for multiple capacity settings and a small mix of specialty engines. They also have small I/O attachment requirements and very low growth requirements.
Which z Systems capacity setting would be the lowest capacity starting point for the customer discussion?

A. zBC12 A01
B. z13 401
C. z13 701
D. zBC12 M01

Answer: A

Explanation:
Reference:
http://www-01.ibm.com/common/ssi/ShowDoc.wss?docURL=/common/ssi/rep_ca/1/897/ENUS113-121/index.html&request_locale=en

Question: 4

A z/OS customer is running on a zBC12 machine and is having a batch window problem.
Which of the following would be the best first step to address this problem?

A. Propose upgrade to new machine with faster processors.
B. Propose technical analysis of the batch window.
C. Propose additional memory on the zBC12.
D. Recommend IDAA to accelerate batch processing.

Answer: B

Question: 5

A financial company wants to improve their real-time fraud detection for ATM cash withdrawals. They are implementing mathematical based models to determine the fraudulent probability of every transaction.
Which z13 feature should be discussed with the customer?

A. Forward Error Correction (FEC)
B. Single Instruction Multiple Data (SIMD)
C. Simultaneous Multithreading (SMT)
D. Elliptic Curve Cryptography (ECC)

Answer: B